Though it is causing significant back-ups at peak traffic hours, a $3.67-million project to install “force-main” underground sewer lines along a portion of Willow Street from Dawson to Orange avenues in Signal Hill is moving along with no problems, according to the County.
Ted Brodeur, assistant resident engineer with County Sanitation Districts for Los Angeles County, said increasing workers at the site has helped facilitate the progress of the undertaking.
“The project is moving along nicely,” Brodeur said. “The contractor has doubled his work force and is working at multiple locations simultaneously in order to complete the project by the mid-August timeframe.”